Scottish Water: Campbeltown WWTW E: Letter 1
Introduction
Happy 2009! Here’s to a prosperous year for us all.
Scottish Water is due to commence the next part of the proposed Waste Water Improvement Project for Campbeltown, which was outlined recently at the Open day in Campbeltown Aqualibrium and also advertised in the local press (Campbeltown Courier (05/12/2008). We would like to thank everyone that attended the Open day and who have worked with us over 2008. Your involvement is certainly appreciated.
At the Open day, many attendees wished to be kept informed on a more regular basis. This E:Letter is the first “round robin” and Scottish Water are committed to keeping this regular communication going.
The construction phase of Work Package 1 of the project is due to commence on site at Slaty Farlan Waste Water Treatment Plant. The following should hopefully gove you some backgournd in how we have got to this stage.
Planning Applications
Planning Application for Work Package 1 has been submitted to Argyll & Bute Council on 16th December 2008.
Campbeltown – Work Package 1 - Initial construction activities
A major benefit of this work will be to reduce the number of spills from Kinloch Park Pumping Station by increasing the capacity of the works. The first operation to be undertaken is site establishment and earthworks to accommodate the additional treatment process. This will be happening at the Slaty Farlan Waste Water Treatment Works. You should see the site establishment starting mid January 09.
Liaison with Local Residents & Community
As a matter of course, we are receiving a number of queries about the project, either directly or by email. Scottish Water Technical Communication Team are in the process of setting up a local Community Forum to communicate project activities to members of the local community via representatives on this forum.
There will be a more comprehensive display of the project in the Campbeltown Library in January and this will be updated with upcoming works information as the project progresses. We launched the use of these displays at the Open day and it was a great success.
We will also continue to liaise and engage with affected landowners and occupiers in advance of our works.
In the New Year, we will provide an indicative programme showing the likely timescales for Work Package 1-Civil works, this will be shared with landowners, neighbours and community councils/forums. Also, the “Campbeltown” section of the Scottish Water website is being revamped and this information and more will be published for public viewing.
Work on the ground
Construction photos will be available to view on our project website and on display in the Campbeltown Library as the work progresses; these will continue to be updated at regular intervals. Aerial photos of Campbeltown are already on display in Campbeltown library.
A summary of some of our recent work at Campbeltown
Completed Works
• Design is progressing on all Work Packages with initial drawings being issued to the contractor (Lagan-EPS) for Work Packages 1,2 and 4.
• Waste water sampling at both Kinloch Park Sewerage Pumping Station and Slaty Farlan Waste Water Treatment Works.
Ongoing/Planned Works
• Bulk excavation is to commence at Slaty Farlan WwTW in January 2009
• Preparation for concrete slab at Slaty Farlan WwTW in January 2009.
• New construction site offices will be delivered & erected at Slaty Farlan WwTW site in January.
• Onsite haul roads will be constructed as required within the site.
Making Contact
Updates will always be posted on our project website as and when available. If you would like to contact Scottish Water about the improvements works at Kinloch Park Pumping Station or Slaty Farlan Waste Water Treatment Works associated pipelines/ancillary work in Campbeltown, you can:
• Phone: Customer Helpline: 0845 601 8855
• E-mail:
campbeltown@scottishwater.co.uk • Write to: Campbeltown WWTW Project, Scottish Water, PO Box 8855, Edinburgh, EH10 6YQ
• Or visit our website:
http://www.scottishwater.co.uk/campbeltown•