Campbeltown Waste Water Treatment Improvements (with photos)

Forum publicising and discussing local issues and news in general.

Campbeltown Waste Water Treatment Improvements (with photos)

Postby Kintyre Forum News » Thu Sep 24, 2009 11:22 pm

Campbeltown Waste Water Treatment Improvements
Scottish Water is committed to improving the treatment of waste water in Campbeltown.

We will provide information on where and when we will be working via infromation events, press statements, newsletters and throughout this section.

Latest News August 2009
Work Package (WP) 1 & 2
Contractor: LEPS


Progress so far:
WP1 is completed with the exception of lighting and system integration.
The Civil work associated with WP2 is substantially complete.
The biological treatment plant, Submerged Aerated Filter (SAF) has been installed and Commissioning is underway.
The SAF plant covers are being installed.
The new membranes have been installed in Aeration Lane 3.
The drain down and cleaning of Aeration Lane 1 is well underway.
Underway with installation of additional digital inputs to flow meter.
Commenced painting of blue tank at Kinloch Park Pumping Station.

Anticipated Work for next period:
Continue commissioning of SAF plant.
Replace Flap Valve on Kinloch Park Pumping Station outfall.
Complete drain down of Aeration Lane 1.
Replace stainless steel pipework and membranes in Lane 1.
Complete painting of Blue Tank
Service and install Actuators.


Work Package (WP) 3 & 4
Contractor: Morrison Construction


Kinloch Park Pumping Station (KPPS) outfall extension nearing completion .

Installation of Storm Rising Main:
Storm rising main (land section): Archaeological watching brief completed; delivery of pipe sections; jointing & installation of pipe 90% complete.
Storm rising main (submarine section): Woodstock barge has sailed into Campbeltown Loch on 1 September 2009.

Low Askomil improvements – all MH cover levels lowered (cover detail to be confirmed); sewer protection (stone cladding); breather pipe reinstatement and stone clad 80% complete.

Meadows Avenue De-dualing – underway.

Anticipated Work for Next Month
Additional remedial works on Meadows Road

Complete KPPS outfall extension

Commence fitting ballast collars to Marine Rising Main.

Construction of Cofferdam at sea wall

Work Package (WP) 5


Tenders issued for the next work package.
--------------------------------------------------------------------------------
Sign up for our newsletter by emailling: campbeltown@scottishwater.co.uk
Last edited by Kintyre Forum News on Sun Oct 18, 2009 3:37 pm, edited 1 time in total.
If you have a news article or event please post here or e-mail us at kfn@campbeltown.info

www.campbeltown.info - www.visitkintyre.info -
www.kintyreaccommodation.com - www.kintyregolf.com
User avatar
Kintyre Forum News
Forum Addict
Forum Addict
 
Posts: 2793
Joined: Fri Feb 03, 2006 9:36 pm


Campbeltown Waste Water Treatment Improvements

Postby Kintyre Forum News » Sun Oct 18, 2009 3:36 pm

Interesting to see the work being carried out by Morrison Enpure as part of the Waste Water Treatment improvements in Campbeltown (see photos below). During the summer Morrison Enpure installed the 1600mm diameter extension to Kinlock Park Puming Station and fixed the concrete weight collars to the 1.5km of 710mm diameter pipe that crosses Campbeltown Loch.

The pipe has now been sunk to the seabed and the present works, involving the 75 tonne crane barge "Woodstock", are centered on jetting a trench into the seabed, placing the pipe within the trench and then backfilling the seabed.

The barge started at approximately the third point of the length and is working towards the Esplanade. When this section is complete the barge will return to the start point and commence workng towards Trench Point.

For more information on the whole project please see http://www.scottishwater.co.uk/campbeltown

Image

Image

Image

Image



Work Package (WP) 3 & 4
Contractor: Morrison Construction

Kinloch Park Pumping Station (KPPS) outfall extension nearing completion .

Installation of Storm Rising Main:
Storm rising main (land section): Archaeological watching brief completed; delivery of pipe sections; jointing & installation of pipe 90% complete.
Storm rising main (submarine section): Woodstock barge has sailed into Campbeltown Loch on 1 September 2009.

Low Askomil improvements – all MH cover levels lowered (cover detail to be confirmed); sewer protection (stone cladding); breather pipe reinstatement and stone clad 80% complete.

Meadows Avenue De-dualing – underway.

Anticipated Work for Next Month
Additional remedial works on Meadows Road

Complete KPPS outfall extension

Commence fitting ballast collars to Marine Rising Main.

Construction of Cofferdam at sea wall
If you have a news article or event please post here or e-mail us at kfn@campbeltown.info

www.campbeltown.info - www.visitkintyre.info -
www.kintyreaccommodation.com - www.kintyregolf.com
User avatar
Kintyre Forum News
Forum Addict
Forum Addict
 
Posts: 2793
Joined: Fri Feb 03, 2006 9:36 pm


Re: Campbeltown Waste Water Treatment Improvements (with photos)

Postby jdcarra » Mon Oct 19, 2009 12:56 am

Two minds work alike KFN :wink: .
Pics taken on Friday afternoon with contractors trying to move the pipeline which was off track. A second breach of the seawall was now needed for the pipe to connect to the pumping station.

Image
Image
Image
Image
Image
Image
Carradale's local website

www.the-carradale-goat.co.uk
User avatar
jdcarra
Forum Addict
Forum Addict
 
Posts: 1719
Joined: Fri Dec 09, 2005 9:56 am
Location: Carradale Glen


Re: Campbeltown Waste Water Treatment Improvements (with photos)

Postby Kintyre Forum News » Fri Jan 29, 2010 12:19 am

General Update

The first four of five phases of improvements to Campbeltown’s waste water network - to increase the pumping capacity from Kinloch Park Pumping Station to Slaty Farlan WWTW – have been completed and will help reduce the number of discharges into Campbeltown Loch. This work includes a rising main, whose route includes a stretch beneath the sea. Contractors Black & Veatch are due to start work on the fifth phase of work, the long-term solution, in April. This will improve the pumping station and provide storm treatment at the WWTW and increased foul treatment.
If you have a news article or event please post here or e-mail us at kfn@campbeltown.info

www.campbeltown.info - www.visitkintyre.info -
www.kintyreaccommodation.com - www.kintyregolf.com
User avatar
Kintyre Forum News
Forum Addict
Forum Addict
 
Posts: 2793
Joined: Fri Feb 03, 2006 9:36 pm



Return to Local News and Issues

Who is online

Users browsing this forum: No registered users and 7 guests