Campbeltown Waste Water Treatment Improvements
Scottish Water is committed to improving the treatment of waste water in Campbeltown.
We will provide information on where and when we will be working via infromation events, press statements, newsletters and throughout this section.
Latest News August 2009
Work Package (WP) 1 & 2
Contractor: LEPS
Progress so far:
WP1 is completed with the exception of lighting and system integration.
The Civil work associated with WP2 is substantially complete.
The biological treatment plant, Submerged Aerated Filter (SAF) has been installed and Commissioning is underway.
The SAF plant covers are being installed.
The new membranes have been installed in Aeration Lane 3.
The drain down and cleaning of Aeration Lane 1 is well underway.
Underway with installation of additional digital inputs to flow meter.
Commenced painting of blue tank at Kinloch Park Pumping Station.
Anticipated Work for next period:
Continue commissioning of SAF plant.
Replace Flap Valve on Kinloch Park Pumping Station outfall.
Complete drain down of Aeration Lane 1.
Replace stainless steel pipework and membranes in Lane 1.
Complete painting of Blue Tank
Service and install Actuators.
Work Package (WP) 3 & 4
Contractor: Morrison Construction
Kinloch Park Pumping Station (KPPS) outfall extension nearing completion .
Installation of Storm Rising Main:
Storm rising main (land section): Archaeological watching brief completed; delivery of pipe sections; jointing & installation of pipe 90% complete.
Storm rising main (submarine section): Woodstock barge has sailed into Campbeltown Loch on 1 September 2009.
Low Askomil improvements – all MH cover levels lowered (cover detail to be confirmed); sewer protection (stone cladding); breather pipe reinstatement and stone clad 80% complete.
Meadows Avenue De-dualing – underway.
Anticipated Work for Next Month
Additional remedial works on Meadows Road
Complete KPPS outfall extension
Commence fitting ballast collars to Marine Rising Main.
Construction of Cofferdam at sea wall
Work Package (WP) 5
Tenders issued for the next work package.
--------------------------------------------------------------------------------
Sign up for our newsletter by emailling: campbeltown@scottishwater.co.uk